Report month July 2026June 2026May 2026April 2026March 2026February 2026January 2026December 2025November 2025October 2025September 2025August 2025July 2025June 2025May 2025April 2025March 2025February 2025January 2025December 2024November 2024October 2024September 2024August 2024July 2024June 2024May 2024April 2024March 2024February 2024December 2023November 2023October 2023September 2023July 2023June 2023May 2023April 2023March 2023February 2023December 2022November 2022October 2022
Stages are Council’s own report headings; a quotation reported after the fact is kept apart from an advertised tender.
| Reference | Description | Stage | Month | Supplier as reported | Value | Source |
|---|---|---|---|---|---|---|
| W2870-22 | Regional Kerbside Collection Services (RKC8) - Joint Tender FIL19/04045 | Under evaluation | November 2022 | — | — | Information Report captured 09 Aug 2026 |
| W2900-22 | Birallee Park Electronic Scoreboard | Under evaluation | November 2022 | — | — | Information Report captured 09 Aug 2026 |
| W2908-22 | La Trobe Sports Field Lighting | Under evaluation | November 2022 | — | — | Information Report captured 09 Aug 2026 |
| W2916-22Q | Les Cheesly Oval Infrastructure - Shed Construction | Awarded | November 2022 | — | — | Information Report captured 09 Aug 2026 |
| W2917-22Q | Les Cheesly Oval Infrastructure - Coaches Timekeeper Box | Under evaluation | November 2022 | — | — | Information Report captured 09 Aug 2026 |
| W2939-22Q | Wodonga Liquor and Gambling Policy and Strategy | Awarded | November 2022 | — | — | Information Report captured 09 Aug 2026 |
| W2942-22Q | Building Condition & Defect Survey and Report | Awarded | November 2022 | — | — | Information Report captured 09 Aug 2026 |
| W2943-22Q | Woodland Street Drainage Improvements | Under evaluation | November 2022 | — | — | Information Report captured 09 Aug 2026 |
| W2944-22 | Racecourse Exhibition Centre Redevelopment - Electrical Works | Awarded by the CEO | November 2022 | Watters Electrical Pty Ltd | $232,469 | Information Report captured 09 Aug 2026 |
| W2946-22Q | Solar Carpark Feasibility Study | Awarded | November 2022 | — | — | Information Report captured 09 Aug 2026 |
| W2953-22Q | Baranduda Fields Tree Plantation Timber Removal | Under evaluation | November 2022 | — | — | Information Report captured 09 Aug 2026 |
| W2957-22Q | Panel of providers for Infrastructure requirements for various events | Awarded | November 2022 | — | — | Information Report captured 09 Aug 2026 |
| W2971-22Q | Panel to supply landscaping plants | Awarded | November 2022 | — | — | Information Report captured 09 Aug 2026 |
| W2975-22Q | Provision of services for the towing and disposal of abandoned vehicles | Advertised | November 2022 | — | — | Information Report captured 09 Aug 2026 |
| W2978-22Q | Design of traffic signals at two sites | Under evaluation | November 2022 | — | — | Information Report captured 09 Aug 2026 |
| W2979-22 | Panel of Providers for the Provision of Drainage & Creek Line Maintenance | Under evaluation | November 2022 | — | — | Information Report captured 09 Aug 2026 |
| W2981-22CE | Pathway UX Platform Application Migration | Awarded | November 2022 | — | — | Information Report captured 09 Aug 2026 |
| W2983-22Q | Moorefield Park Drive Centre Median Construction | Under evaluation | November 2022 | — | — | Information Report captured 09 Aug 2026 |
| W2984-22Q | Supply and install rear yard sand and rock bays at depot | Awarded | November 2022 | — | — | Information Report captured 09 Aug 2026 |
| W2986-22CE | Infor Pathway Authorised Functions | Awarded | November 2022 | — | — | Information Report captured 09 Aug 2026 |
| W2987-22Q | Shade Sail supply and installation for Gayview Park Playground and Henrika Kuljurgies Reserve | Advertised | November 2022 | — | — | Information Report captured 09 Aug 2026 |
| W2995-22Q | Termite Management Action Plan - Block 19 BME | Advertised | November 2022 | — | — | Information Report captured 09 Aug 2026 |
| W2996-22CE | Bike Hub - Architectural Design | Awarded | November 2022 | — | — | Information Report captured 09 Aug 2026 |
| W3001-22Q | White Box Rise Retaining wall | Advertised | November 2022 | — | — | Information Report captured 09 Aug 2026 |
| W3006-22Q | Supply and delivery of two out front 72" deck, rear discharge mowers complete with enclosed factory fitted... | Advertised | November 2022 | — | — | Information Report captured 09 Aug 2026 |
| W3007-22Q | Supply and delivery of a mower 40 to 50HP front deck with catcher | Advertised | November 2022 | — | — | Information Report captured 09 Aug 2026 |
| W3008-22Q | Supply and delivery one (1) large area rotary three-winged mower 45 to 50 HP with enclosed factory fitted... | Advertised | November 2022 | — | — | Information Report captured 09 Aug 2026 |
| W3009-22 | Five Hybrid, automatic, MWB trucks minimum 8,500 GVM 12,000 GCM with attached tipping body | Advertised | November 2022 | — | — | Information Report captured 09 Aug 2026 |
| W3011-22Q | Supply and delivery of one (1) Reel Mower 45 to 50 HP with enclosed factory fitted air-conditioned ROPS... | Advertised | November 2022 | — | — | Information Report captured 09 Aug 2026 |
| W3013-22Q | One trailer mounted water jetting drain cleaner machine 75lpm @4000psi. | Advertised | November 2022 | — | — | Information Report captured 09 Aug 2026 |
| W3019-22Q | Supply and construct farm style storage shed | Advertised | November 2022 | — | — | Information Report captured 09 Aug 2026 |
| W3021-22 | Bonegilla Asbestos Removal | Advertised | November 2022 | — | — | Information Report captured 09 Aug 2026 |
| W3022-22Q | Castle Heights Playground Renewal | Advertised | November 2022 | — | — | Information Report captured 09 Aug 2026 |
| W3024-22Q | Bonegilla Asbestos Removal Hygienist Services | Advertised | November 2022 | — | — | Information Report captured 09 Aug 2026 |
| W3026-22CE | Development Contributions - Policy and Procedures | Awarded | November 2022 | — | — | Information Report captured 09 Aug 2026 |